
we provide Refined PMI PMI-RMP exam price which are the best for clearing PMI-RMP test, and to get certified by PMI PMI Risk Management Professional. The PMI-RMP Questions & Answers covers all the knowledge points of the real PMI-RMP exam. Crack your PMI PMI-RMP Exam with latest dumps, guaranteed!
Online PMI-RMP free questions and answers of New Version:
NEW QUESTION 1
You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?
Answer: C
NEW QUESTION 2
Consider the risk probability-impact matrix in the figure given below:
If Risk B happens in this project, how much will be left in the contingency reserve?
Answer: A
NEW QUESTION 3
The Identify Risk process determines the risks that affect the project and document their characteristics. Why should the project team members be involved in the Identify Risk process?
Answer: A
NEW QUESTION 4
You are the project manager of the KJH Project and are working with your project team to plan the risk responses. Consider that your project has a budget of $500,000 and is expected to last six months. Within the KJH Project you have identified a risk event that has a probability of .70 and has a cost impact of $350,000. When it comes to creating a risk response for this event what is the risk exposure of the event that must be considered for the cost of the risk response?
Answer: A
NEW QUESTION 5
You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?
Answer: B
NEW QUESTION 6
Frank is the project manager of the NHL Project for his company and he is starting the risk identification process for the project. Frank needs to ensure that the correct stakeholders are interviewed as part of risk identification. What document will help Frank to communicate and solicit inputs of the project stakeholders during risk identification?
Answer: D
NEW QUESTION 7
Jeff, a key stakeholder in your project, wants to know how the risk exposure for the risk events is calculated during quantitative risk analysis. He is worried about the risk exposure which is too low for the events surrounding his project requirements. How is the risk exposure calculated?
Answer: B
NEW QUESTION 8
You work as a project manager for TechSoft Inc. You are preparing to plan risk responses for your project with your project team. How many risk responses are available for a positive risk event in the project?
Answer: B
NEW QUESTION 9
During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
Answer: A
NEW QUESTION 10
You are the project manager of a large project that will last four years. In this project, you would like to model the risk based on its distribution, impact, and other factors. There are three modeling techniques that a project manager can use to include both event-oriented and project-oriented analysis. Which modeling technique does NOT provide event-oriented and project-oriented analysis for identified risks?
Answer: B
NEW QUESTION 11
You are the project manager for Genpact Inc. You have established quarterly risk management meetings. Which of the following is not a component of a risk management meeting?
Answer: D
NEW QUESTION 12
Linda is the project manager of the NAB Project. One of the risks her project team has identified is too dangerous for the project team to manage internally so she has hired a vendor to complete this portion of the project and to manage the identified risk. What risk response has Linda used in this instance?
Answer: A
NEW QUESTION 13
Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?
Answer: A
NEW QUESTION 14
Which of the following is a risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold?
Answer: D
NEW QUESTION 15
You and your project team are just starting the risk identification activities for a project that is scheduled to last for 18 months. Your project team has already identified a long list of risks that need to be analyzed. How often should you and the project team do risk identification?
Answer: C
NEW QUESTION 16
Which one of the following is the only output for the qualitative risk analysis process?
Answer: C
NEW QUESTION 17
Management has asked you to perform a risk audit and report back on the results. Bonny, a project team member asks you what a risk audit is. What do you tell Bonny?
Answer: B
NEW QUESTION 18
There are seven risk responses, a project manager can use to address risk events. Which one of the following is a risk response that is appropriate for positive or negative risk events depending on the scenario in the project?
Answer: B
NEW QUESTION 19
You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?
Answer: D
NEW QUESTION 20
You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?
Answer: C
NEW QUESTION 21
......
P.S. Easily pass PMI-RMP Exam with 137 Q&As DumpSolutions.com Dumps & pdf Version, Welcome to Download the Newest DumpSolutions.com PMI-RMP Dumps: https://www.dumpsolutions.com/PMI-RMP-dumps/ (137 New Questions)